煤炭工程 ›› 2025, Vol. 57 ›› Issue (8): 42-48.doi: 10. 11799/ ce202508007

• 施工技术 • 上一篇    下一篇

上行开采渐变煤柱下沿空巷道分区协同支护技术研究

房万伟,郝清旺,董金法,陈建刚,刘统申,张勇,刘其路,张吉祥   

  1. 1. 内蒙古上海庙矿业有限责任公司,内蒙古 鄂尔多斯 016200

    2. 新矿内蒙古能源有限责任公司,内蒙古 鄂尔多斯 016200

    3. 中国矿业大学(北京)力学与土木工程学院,北京 100083

    4. 中国矿业大学(北京)内蒙古研究院,内蒙古 鄂尔多斯 017010

  • 收稿日期:2025-07-25 修回日期:2025-08-08 出版日期:2025-08-11 发布日期:2025-09-11
  • 通讯作者: 房万伟 E-mail:505776401@qq.com

Mechanism of gob-side roadway large deformation with gradient coal pillar in ascending mining and the sectional collaborative support technology

  • Received:2025-07-25 Revised:2025-08-08 Online:2025-08-11 Published:2025-09-11
  • Contact: Wanwei Fang E-mail:505776401@qq.com

摘要:

为解决上行开采渐变煤柱条件下沿空巷道稳定性控制的难题,以榆树井煤矿1206工作面辅运巷为工程背景,采用现场调研、理论分析与现场试验相结合的方法,系统揭示该条件下沿空巷道的变形破坏机理。基于协同支护理论,提出分区协同支护设计方案,并通过现场试验段巷道变形监测验证其控制效果。研究结果表明:1206辅运巷大变形破坏的主要诱因包括围岩力学性质劣化、遇水软化、工程应力扰动及煤柱渐进变窄等;通过弹塑性理论计算,确定该沿空巷道保护煤柱最小宽度为15m,并据此将巷道划分为强影响区、中影响区与弱影响区,针对性地形成各分区控制对策并开展现场应用;监测数据显示,新技术应用后巷道围岩累计变形量平均降低30%以上,有效遏制了上行开采渐变煤柱条件下沿空巷道的围岩大变形。

关键词:

上行开采 , 渐变煤柱 , 沿空巷道 , 分区支护 , 围岩大变形 , 弹塑性理论

Abstract:

In order to solve the difficulty in stability control of gob-side roadway under gradient coal pillars in ascending mining, taking the auxiliary transportation roadway of 1206 working face in Yushujing Coal Mine as the engineering background, the deformation and failure mechanism of gob-side roadway is revealed by field investigation, theoretical analysis and field test. Based on the theory of collaborative support, the design scheme of sectional collaborative support is put forward, and the control effect is verified by the deformation monitoring of roadway in field test. The research shows that the causes of large deformation and failure of auxiliary roadway in No. 1206 working face are poor mechanical properties of surrounding rock, water softening, engineering stress disturbance and gradual narrowing of coal pillar. According to the elastic-plastic theory calculation, the minimum width of the protective coal pillar for the gob-side roadway is 15 m. Based on this, the roadway is divided into three influence sections: strong, medium and weak sections and the control countermeasures of different sections are formed and applied on site. The monitoring data show that the cumulative deformation of the roadway surrounding rock is reduced by more than 30% after applying the new technology, and the surrounding rock large deformation of the gob-side roadway with gradient coal pillar in the ascending mining is effectively controlled.

中图分类号: